AWS – Commssioning and modifications to wave energy device

Working as a contractor to Sequentec, I produced the detailed design for several PLC system panels used on this prototype wave energy device. Later, I was asked to commission the electrical equipment and cabling during assembly at the structural fabricators in Glasgow. To do this I needed to produce commissioning … Continue reading

Mocean – Large scale wave energy device for deployment at EMEC, Orkney

The electrical systems for this large, offshore wave energy device were tested in Rosyth before being assembled into its structure at the steelwork fabricator’s workshop in Cowdenbeath, Scotland. Working as a subcontractor to Sequentec, I supported the development of this device over several years. I designed several electrical panels as … Continue reading

ScotRenewables – Commissioning tidal device

commissioning tidal device in shipyard
Tidal device at Harland & Wolff during electrical commissioning

I was contracted for 3 weeks to begin commissioning the electrical systems of the ScotRenewables (now Orbital Marine Power) 2MW tidal device at Harland and Wolff shipyard in Belfast, Ireland. In this time I created a set of commissioning documents and tested a large part of the electrical panels, sensors and cabling. Unfortunately, I was only available for 3 weeks as I had another contract already arranged, but I left template documents and a commissioning plan to allow the customer to continue this testing themselves.